Work is underway on this multiplex which is expected to go live in September 2013.
For both Ridge Hill and Malvern TX the transmitters are expected to be delivered this week (8th July). Electrical installation is scheduled from 12th August with antenna work on the 19th. Commissioning is scheduled for 26th August and we anticipate these transmitters will be operational in early September. Bromsgrove will be commissioned from 2nd September, so anticipated operational from mid-September .
Our transmission subcontractor has been undertaking the design work for the contribution network. Current delays relating to the BT distribution network may affect telecom delivery and so may impact on launch dates.